ACTION PLANNING ACCORDING TO HOLIDAYS
BSAT PARAMETER
SAT > BSAT > Configuration Settings > Parameters In the parameter value "Which days should the working days be?" numbered "82", the numerical values of the days are written as 1 (Monday), 2 (Tuesday), 3 (Wednesday), 4 (Thursday), 5 (Friday), 6 (Saturday), 7 (Sunday) separated by commas. In this way, working days and holidays can be determined.

Then, in the SAT > Action > Action Parameters menu, click "Should holidays be taken into account when opening actions? (E/H)" parameter value is written as "E". In this way, the days determined during the action planning will be calculated based on the working days. With the configuration of the parameter value No. 49 as specified, the parameter value No. "50" "Actions can be postponed forward/backward according to holidays (Forward: I, Backward: G)" is determined. If the relevant parameter value is selected as "Next", it will be set to the next business day, and if it is set to "Back", it will give the action plan to the previous business day.